A single 15-minute demand spike in January can lock your facility into inflated billing for the next 11 months. Here’s how ratchet clauses work—and how to avoid them.
What Is a Ratchet Clause?
Most federal facilities pay two types of charges on their utility bills:
- Energy charges: What you actually used (measured in kWh)
- Demand charges: Your peak usage during any 15-minute window (measured in kW)
Demand charges can represent 30–60% of your total bill—but they’re based on a single moment each month.
The ratchet clause makes it worse.
If your utility contract includes a ratchet clause (also called a “minimum demand” provision), you don’t just pay for your actual peak each month. You pay for the greater of:
- Your actual peak demand this month, OR
- 85% of your highest peak from the past 12 months
How This Costs You Money
Example: The January Spike
January: A chiller startup coincides with a grid voltage sag. Your facility hits a 15-minute peak of 5,000 kW.
February–December: Your normal peak is only 3,800 kW.
Without ratchet clause: You pay demand charges based on 3,800 kW each month.
With ratchet clause: You pay demand charges based on 4,250 kW (85% of 5,000 kW) every month—even though you never use that much again.
The cost: At $15/kW/month, that extra 450 kW costs you $74,250 per year—for capacity you never used after January.
How to Check If You Have a Ratchet Clause
Step 1: Pull your utility tariff (usually available on your utility’s website under “Rate Schedules”)
Step 2: Look for language like:
- “Minimum demand”
- “Ratchet provision”
- “85% of annual peak”
- “12-month rolling maximum”
Step 3: Compare your billed demand to your actual demand
If your billed demand stays suspiciously consistent month-to-month (even when your usage varies), you’re likely in a ratchet.
How to Avoid Ratchet Penalties
Strategy 1: Identify and eliminate anomalous peaks
Most ratchet-triggering peaks aren’t from normal operations—they’re from:
- Equipment startups at the wrong time
- Grid voltage sags forcing motors to draw excess current
- Power factor penalties creating reactive power spikes
Our forensic analysis identifies which peaks are anomalies vs. legitimate operational needs.
Strategy 2: Control when large loads start
If you can delay chiller/pump startups by 30 minutes to avoid coinciding with other loads, you can prevent ratchet-setting peaks.
Requires: Real-time monitoring and automated load controls
Strategy 3: Challenge grid-caused peaks
If your peak was caused by a utility-side voltage drop (not your equipment), you may be able to dispute the charge.
Requires: Time-synchronized data proving the utility caused the spike
What This Looks Like in Practice
Facility: Mid-size federal installation
Problem: January chiller startup during grid voltage sag created 5,200 kW peak
Ratchet baseline: 4,420 kW (85% of 5,200) for next 11 months
Normal peak: 3,700 kW
Excess demand billed: 720 kW × 11 months × $15/kW/month = $118,800 wasted
Solution: Forensic analysis identified the spike was grid-caused + poor power factor. Utility agreed to remove ratchet penalty after we provided synchronized voltage data.
Savings: $118,800 recovered
Is Your Facility Locked in a Ratchet?
Our $2,500 Quick Scan identifies whether you’re paying for anomalous peaks
Request AnalysisQuestions? Email mica@lisanalytics.net or call (610) 835-6556

Leave a Reply